Westconnex M5 - CPB Dragados Samsung Joint Venture
Sydney Excavation Group Pty Ltd have been engaged by CPB Dragados Samsung JV on this $4.3b revelopment of one of Sydney's major roads.
Scope of Works:
- Excavation Works
- Testing and classification of materials
- Loading and disposal of materials
- Handling of contaminated materials
Duration:
- TBA




Westconnex M4E - CPB Samsung John Holland Joint Venture
Sydney Excavation Group Pty Ltd have been engaged by CPB Samsung John Holland JV on this $3.8b revelopment of one of Sydney's major road.
Scope of Works:
- Excavation Works
- Testing and classification of materials
- Loading and disposal of materials
- Handling of contaminated materials
Duration:
- 8 weeks

84-86 Kiora Road, Miranda - CBS Projects Pty Ltd
Sydney Excavation Group Pty Ltd were engaged by CBS Project on this mixed used development
Scope of Works:
- Demolition and removal of existing shop front
- Handling of asbestos
- Bulk Excavation (15m Depth)
- Detail Excavation
- Shoring Works (Piling, Shotcrete & Anchoring)
Duration:
- 12 weeks
150 Mowbray Road & 670-680 Willoughby Road, Willoughby - Ceerose Pty Ltd
Sydney Excavation Group Pty Ltd were engaged by Ceerose Pty Ltd on this $95m mixed used development comprising 110 residential apartments, bulky goods retial & commercial floorspace.
Scope of Works:
- Demolition and removal of 2x 3 Storey commerical buildings including basements
- Handling of asbestos
- Temporary propping of existing basement and retain
- Underpinning
Duration:
- 12 weeks




108 Herring Road, Marsfield - John Lyng Commerical Builders Pty Ltd
Sydney Excavation Group Pty Ltd were engaged by John Lyng Commerical Builders Pty Ltd on this $50m commerical development.
Scope of Works:
- Demolition and removal of existing liquor shop
- Demolition and removal of existing carpark
- Bulk Excavation - 10,000m3
- Detail Excavation
- Re Classification and removal of ENM material
Duration:
- 8 weeks



7 Loftus & 37-38 New Beach Road, Darling Point - Bay State Constructions Pty Ltd
Sydney Excavation Group Pty Ltd were engaged by Bay State Constructions Pty Ltd on this residential development
Scope of Works:
- Demolition of existing residential structure
- Bulk Excavation - 2,500m3
- Bulk Excavation of neighbouring property - 1,000m3
- Preparing for shoring works
- Detail Excavation
Duration:
- 9 weeks


2 Wolseley Road, Darling Point - Bay State Constructions Pty Ltd
Sydney Excavation Group Pty Ltd were engaged by Bay State Constructions Pty Ltd on this residential development
Scope of Works:
- Demolition of existing residential structure
- Bulk Excavation - 3,000m3
- Preparing for shoring works
- Detail Excavation
Duration:
- 10 weeks